Made possible by 10th Mountain’s commitment to quality & sustainability… Base of Operations is critically important to keeping the huts in good shape and available far into the future.

Al Beyer © 2016

Base of Operations | Projected Budget

 

Main Building | 2,400 sq.ft.                      $350,000

Vehicle Shed | 576 sq.ft.                            $60,000

Tool Shed | 200 sq.ft.                                $20,000

Utilities                                                      $70,000

Professional Fees                                    $50,000

Land Acquisition                                      $85,000

 

                   Total Project Budget            $635,000

(In-kind Contribution of Land)   –$(85,000)

 

Total Funds Needed      $550,000

 

1280 Ute Avenue | Suite 21

Aspen, Colorado 81611

970/925-4554

E-MAIL donate@huts.org